• Mining Right Renewal.
Q1 2021
  • Contract Agreement between Apex Middelvlei and Zambesi.
  • Exploration of Portion 3 & Portion 48 and Andrew's Pit concept designs.
  • Trenching to explore reef outcrops.
  • Sampling, assay and valuation of orebody.
  • Bulk sampling.
  • WAD SAMPLING and analysing heap leach recovery process and feasibility.
  • Flotation recovery process and feasibility.
  • Historical and geological data from Shango.
  • Water testing.
Q2 2021
  • Extreme sampling and geological programme commenced.
  • Establishment of Apex Team.
  • Exploration of mineralised zone.
  • Portion 3 exploration.
  • Sampling, assay and valuation of orebody.
  • Tonnage estimation.
  • Grade distribution and metallurgical.
  • Testing Maelgwyn.
  • Vat leach recovery process and feasibility.
Q3 2021
  • Exploration and sampling Box Cut Area and all stockpile dumps.
  • Assay and valuation of orebody.
  • Drilling and sampling of Box Cut Area.
  • Feasibility of Box Cut Area.
  • Water Use License submission.
  • Environmental Management Program updating.
  • Section 11 application.
  • Interact Sibanye on Toll Treatment.
  • Undercut of Box Cut for Pit 4 and Steffany’s block options.
  • Combined valuation mineralised and Black Reef.
Q4 2021
  • EMP/Water Use License renewal Nov. 2021.
  • Acquisition of gold plant Nov. 2021.
  • Middelvlei Apex Zambesi Gold Agreement.
  • Plant acquisition.
  • Road maintenance and establishment.
  • Rehabilitation of Office Pit (Plant footprint design).
  • Mine Plan and scenarios.
  • Modelling and scheduling.
  • New site office area establishment.
  • CPR conclusion.
Q1 2022
  • Plant footprint construction.
  • New site office initiation.
  • Water Sealing Programme.
  • Acquire equipment for development.
  • Exploration and geological core drilling.
  • Sign off Mining Plan.
  • Establish porthole.
  • Modelling and rock engineer recommendations.
  • SLP negotiations.
  • Acquire Eskom power lines.
Q2 2022
  • Drilling and blasting established porthole.
  • Acquire winder for decline.
  • Order material for equipment.
  • Acquire sets.
  • Ventilation and compressed air.
  • Labour engagement.
  • Rock engineer permanent support.
  • Design.
Q3 2022
  • Develop start in decline.
  • Stockpile material.
  • Sampling, assay and valuation.
Q4 2022
  • Commissioning of plant.
  • Development of decline.
  • Horizontal development.
  • Raise development.
2020
2021
2022
Q2 2021
  • Zambesi Gold founded.
  • Zambesi Gold (Pty) Ltd registration.
  • Shareholder’s agreement.
Q3 2021
  • Token minting on BSC network (Binance Smart chain) (ZGD).
  • Finalisation of website and token design.
  • Domain registrations.
  • Registration of Custodian Trust.
  • Marketing platform registrations.
Q4 2021
  • Zambesi Gold (Pty) Ltd trademark registration.
  • Gold vault module.
  • Exchange engagements.
  • Pre-private investment sale.
  • NSK Trust account confirmation.
  • Token distribution on Metamask.
  • Production of Middelvlei promotional videos.
  • Website completion
  • Payment integration for ICO.
Q1 2022
  • YouTube influencer engagements.
  • Final approvals for exchange listings.
  • Press releases and marketing platforms.
  • All social media activations.
  • ICO pre-sale launch commence 14 Jan. 2022 @ $0.10c USD.
  • ICO pre-sale second phase 14 Feb. 2022 @ $0.15c USD.
  • ICO initial sale 14 March 2022 @ $0.20c USD.
  • Promotional videos and explanatory videos.
  • Competition for Telegram community members.
Q2 2022
  • ICO initial sales 14 April 2022 until 12 May 2022 @ $0.25c USD.
  • End of ICO sales 12 May 2022.
  • Listing on crypto exchange 14 May 2022 @ $0.30c USD.
  • CMC application.
  • Second exchange application.
Q3 2022
  • Second exchange listing.
  • Promotional mining video.
  • NFT integrations.
  • Explanatory video regarding gold vault.
  • Third exchange application.
  • Zambesi Gold Road Show.
Q4 2022
  • Third exchange listing.
  • New road map.
  • Upgrade of website.
  • NFT registration on blockchain.
2020
  • Mining Right Renewal.
2021
Q1 2021
  • Contract Agreement between Apex Middelvlei and Zambesi.
  • Exploration of Portion 3 & Portion 48 and Andrew's Pit concept designs.
  • Trenching to explore reef outcrops.
  • Sampling, assay and valuation of orebody.
  • Bulk sampling.
  • WAD SAMPLING and analysing heap leach recovery process and feasibility.
  • Flotation recovery process and feasibility.
  • Historical and geological data from Shango.
  • Water testing.
Q2 2021
  • Extreme sampling and geological programme commenced.
  • Establishment of Apex Team.
  • Exploration of mineralised zone.
  • Portion 3 exploration.
  • Sampling, assay and valuation of orebody.
  • Tonnage estimation.
  • Grade distribution and metallurgical.
  • Testing Maelgwyn.
  • Vat leach recovery process and feasibility.
Q2 2021
  • Zambesi Gold founded.
  • Zambesi Gold (Pty) Ltd registration.
  • Shareholder’s agreement.
Q3 2021
  • Exploration and sampling Box Cut Area and all stockpile dumps.
  • Assay and valuation of orebody.
  • Drilling and sampling of Box Cut Area.
  • Feasibility of Box Cut Area.
  • Water Use License submission.
  • Environmental Management Program updating.
  • Section 11 application.
  • Interact Sibanye on Toll Treatment.
  • Undercut of Box Cut for Pit 4 and Steffany’s block options.
  • Combined valuation mineralised and Black Reef.
Q3 2021
  • Token minting on BSC network (Binance Smart chain) (ZGD).
  • Finalisation of website and token design.
  • Domain registrations.
  • Registration of Custodian Trust.
  • Marketing platform registrations.
Q4 2021
  • EMP/Water Use License renewal Nov. 2021.
  • Acquisition of gold plant Nov. 2021.
  • Middelvlei Apex Zambesi Gold Agreement.
  • Plant acquisition.
  • Road maintenance and establishment.
  • Rehabilitation of Office Pit (Plant footprint design).
  • Mine Plan and scenarios.
  • Modelling and scheduling.
  • New site office area establishment.
  • CPR conclusion.
Q4 2021
  • Zambesi Gold (Pty) Ltd trademark registration.
  • Gold vault module.
  • Exchange engagements.
  • Pre-private investment sale.
  • NSK Trust account confirmation.
  • Token distribution on Metamask.
  • Production of Middelvlei promotional videos.
  • Website completion
  • Payment integration for ICO.
2022
Q1 2022
  • Plant footprint construction.
  • New site office initiation.
  • Water Sealing Programme.
  • Acquire equipment for development.
  • Exploration and geological core drilling.
  • Sign off Mining Plan.
  • Establish porthole.
  • Modelling and rock engineer recommendations.
  • SLP negotiations.
  • Acquire Eskom power lines.
Q1 2022
  • YouTube influencer engagements.
  • Final approvals for exchange listings.
  • Press releases and marketing platforms.
  • All social media activations.
  • ICO pre-sale launch commence 14 Jan. 2022 @ $0.10c USD.
  • ICO pre-sale second phase 14 Feb. 2022 @ $0.15c USD.
  • ICO initial sale 14 March 2022 @ $0.20c USD.
  • Promotional videos and explanatory videos.
  • Competition for Telegram community members.
Q2 2022
  • Drilling and blasting established porthole.
  • Acquire winder for decline.
  • Order material for equipment.
  • Acquire sets.
  • Ventilation and compressed air.
  • Labour engagement.
  • Rock engineer permanent support.
  • Design.
Q2 2022
  • ICO initial sales 14 April 2022 until 12 May 2022 @ $0.25c USD.
  • End of ICO sales 12 May 2022.
  • Listing on crypto exchange 14 May 2022 @ $0.30c USD.
  • CMC application.
  • Second exchange application.
Q3 2022
  • Develop start in decline.
  • Stockpile material.
  • Sampling, assay and valuation.
Q3 2022
  • Second exchange listing.
  • Promotional mining video.
  • NFT integrations.
  • Explanatory video regarding gold vault.
  • Third exchange application.
  • Zambesi Gold Road Show.
Q4 2022
  • Commissioning of plant.
  • Development of decline.
  • Horizontal development.
  • Raise development.
Q4 2022
  • Third exchange listing.
  • New road map.
  • Upgrade of website.
  • NFT registration on blockchain.